Jura announces the spudding of the Khanpur 2 well

Jura Energy has spudded the Khanpur 2 well today. The Khanpur 2 well is located in Block 22 in the Central Gas Basin of Pakistan and has been designed as a development well to target the Sui Main Limestone Reservoir at a depth of approximately 1162 meters; the well is expected to take 30 days to drill and will be tied-in to the existing gas processing facilities after a 4 day testing program. The rig will be moved to the Sadiq field immediately thereafter where an additional well will be drilled.
The drilling contractor is the Sichuan Petroleum Administration drilling company of China; Khanpur 2 and Sadiq 2 are the second and third wells of a three well program. The first well of the program, Hasan 3, was successfully drilled in October. Hasan 3 is scheduled to be tied-in to the processing facilities at Block 22 during the month of December.